It's gettin'... it's gettin'... it's gettin' kinda hectic.
BART was held up this morning for about an hour due to-- drum roll please-- a contractors mistake. Yay!!! We totally had snakes on the train as the cause of the delay in this morning's SFist Office Pool. Anyways, what happened was a contractor (no word yet on whether or not they are now considered to be an "ex-contractor") accidentally punctured a water line and the punctured water line showed up as a power outage on the computer. Et viola, the computer shut down the system thinking there was no power anymore. This all happened around 7:15 this morning and was fixed slightly after 8. BART was still playing catch-up last we heard and the roads were little more traffic laden than normal.
See what happens when you hire temps?